AJ Scott

email
call 01668 217 288
fax 01668 217 171

Raising the bar at AJS!

Posted: 25th July 2014

Progress continues in the construction of the new bandmill line at A&J Scott. Further developments have seen the walls and roof of the building completed and this week saw the installation of the overhead crane which will facilitate tasks such as blade changes and movement of equipment into the saw doctor workshop, maintenance tasks and occasional movement of oversize timbers.

Preparations will continue inside the building in readiness for the mill equipment itself being installed during the autumn.

           The crane is prepared for lifting into placeOnwards and upwards!The crane moves into position

 

Posted 27th June 2014

Preparations continue apace for for installation of the new EWD bandmill at A&J Scott.

With the site cleared and foundations in place, construction has progressed well and the building which will house the new production line is taking shape. Within the building, foundations for the bandmill itself are being readied for the installation. The bandmill machinery itself will weigh a combined 24.5 tonnes, with the carriage weighing in at 11 tonnes and the saw at 9 tonnes. The completed installation will stand almost 8 metres high.

Watch this space for further news!

Building progresses The building takes shape Bandmill foundations

 

Posted 14th May 2014

Good progress is made with the demolition and groundworks. Foundations are now being laid for the new building which will house the new production line.

We will keep you up to date as work progresses!

New mill groundworks

 

Work begins on major AJS growth programme

Posted 8th April 2014

Site works are beginning at A&J Scott in the first steps of the company’s latest £4million investment programme.

The company is delighted to announce that it has recently signed contracts with German sawmill machinery manufacturers EWD and PAUL to install a new bandmill at its Northumberland site, as well as make some improvements to the main sawmill production line which was installed in 2007.

The first stages of the programme, already underway, will see the removal of machinery from one of the older re-saw workshops on the site, which will then be demolished completely to allow for construction of a new building to house the new bandmill line. Groundworks and construction will continue during the coming summer months in preparation for the new machinery being installed during the later stages of 2014.

Installation is expected to be fully completed in time for the new line to be operational early in 2015. The new bandmill will be particularly efficient at producing the company’s range of heavy timber products such as railway sleepers, agricultural purlins and other large section products, as well as products within the main fencing range including gateposts, fence posts and rails. The efficient recovery will also increase the company’s output of fence boards, sarking boards and other products.

As part part of this programme, re-work facitilities on site have been reorganised to increase efficiency, while a follow-up programme of works will see upgrades to the company’s main production line in its current Mill 7, which will increase output of the main range of fencing items.

Watch this space for updates as the project progresses throughout the year!

Dismantling begins Machinery is stripped out AJS site works